Installation
Location : Amphur Muang , Kampangphet Province
Machinery : Shin Nippon condensing steam turbine - Reduction gear - Generator 9.9 MW.
Machinery grouting plate preparation
Installation condenser
Installation lubrication oil system
Installation steam turbine - reduction gear and generator
Alignment turbine - reduction gear and generator approved by Mr.Sumida
Assembling inlet lubrication oil piping and outlet oil piping
Machinery complete unit installation and alignment
Location : Amphur Banpong , Ratchaburi Province
Machinery : Shin Nippon condensing steam turbine - Reduction gear - Generator 17.5 MW.
Foundation grouting preparation
Installation condenser
Steam turbine installation and alignment preparation
Reduction gear installation and alignment preparation
Generator installation and alignment preparation
Piping installation and alignment preparation
Final alignment check of steam turbine - reduction gear and generator approved by Shin nippon
Assembling steam turbine cover job done
Finalize job done
Location : Amphur Wangsapung , Loei Province
Machinery : Shin Nippon Back Pressure steam turbine 41 MW. 40 bar Temp 480˚c
Machinery Loading & unloading and complete steam turbine installation
Location : Amphur Khonburi , Nakhon Ratchasrima Province
Machinery : Shin nippon condensing steam turbine axial flow type with Reduction gear - Generator 35 MW.
Foundation grouting preparation
Machining loading and unloading to location for installation
Installation condenser
Location : Amphur Muang Sa keao , Sa keao Province
Machinery : HTC Condensing steam turbine and Reduction gear - Generator 9.9 MW.
Turbine - Reduction gear foundation adjusting and pre-alignment
Reduction gear,Generator foundation adjusting and pre-alignment
Steam turbine,Reduction gear and Generator grouting
Condenser and Gland steam condenser grouting
Lube oil pipe installation
Clean oil filter and oil tank
Lubrication oil flushing preparation
Final alignment and connect coupling
Turbine casing before install insulation jacket